Updated last 18.06.2025
This section provides the following information:
- General information as to the connection of sites of electricity customers to the electricity transmission or electricity distribution networks;
- Information as to who can connect and who can offer electricity supply services;
- Information as to the connection procedure:
- Filing a request for a survey of the conditions for connection;
- Issuance of a written statement by the operator and signing of preliminary connection agreement;
- Conclusion of a connection agreement;
- Design and construction of the technical facilities;
- Commissioning of customer sites and facilities for connection to electricity networks.
The electricity supply system is divided into two networks, and paragraph 1, item 20 and 22 of the additional provisions of the Energy Act (EA) provides definitions thereto:
- Electricity transmission network is a combination of electric power lines and electric facilities serving for transmission, transformation of the electric power of high voltage to medium voltage and redistribution of electric flows.
- Electricity distribution network is a combination of electric power lines and electric facilities of high, medium and low voltage serving for distribution of electric power.
With regard to the connection to the transmission or to the distribution electricity networks, a more detailed regulation is included in Ordinance No. 6 of 28th of March 2024 on the connection of sites to the electricity networks, issued by the Energy and Water Regulatory Commission (EWRC) (the “Ordinance”).
Who can connect to the network and who can offer the service?
Under article 7, paragraph 2 of the Ordinance, a person who meets the following criteria may be connected to the electricity supply network:
- Has a real right to build on the property where the site is or will be constructed;
- Is the owner, user, or tenant of the site to be connected;
- Has notarized consent from the property owner or a lease agreement with the owner and notarized consent for the placement of a movable structure;
- Has a real right to build on the property or within the site where the site or the non-independent facility/installation is or will be constructed, or has a lease agreement and notarized consent from the owner for the placement of a movable structure .
The cases in which a written request for the connection of a site may be submitted are exhaustively enumerated in Article 7, paragraph 1 of the Ordinance. For example: Article 7, paragraph 1, item 1 provides for the case of “the construction of a new site”, while item 3 covers “the reconstruction of a site pursuant of the Spatial Development Act”.
The electricity supply service is provided by the respective network operator of the electricity distribution network.
What is the connection procedure?
Filing a request for a survey of the conditions for connection
The first phase of the procedure is the survey of the conditions for connection of a site of a customer to the electricity network. For this purpose, a written request has to be submitted to the respective network operator depending on the location of the customer’s site, in a form provided by the network operator.
Art 8, para. 2 of the Ordinance sets out the documents that have to be attached to the application:
- A document certifying a real right to build on the property/site in which the site/non-independent facility/installation is or will be constructed – in cases of construction of a new site, construction of a new site with a non-independent facility/installation, reconstruction of a site, and temporary electricity supply to construction sites;
- A document certifying a real right to build on the property/site, or a notarized consent of the property/site owner, or a lease agreement and a notarized consent of the property/site owner – in cases of reconstruction of a site, increase of the connected capacity, creation of a new site through subdivision, change in the number of phases, construction of new connection facilities, electricity supply to undeveloped property, connection of an existing site, restoration of a terminated connection, additional power supply without a change of category, and commencement of supply from a non-independent facility for own consumption only;
- A notarized consent of the property owner or a lease agreement and a notarized consent of the owner – in cases of temporary electricity supply to movable sites.
When the documents provided are incomplete or do not meet the requirements of the Ordinance, the respective network operator notifies in writing the person filing the application within 5 /five/ working days as of the date of filling (Art 8, para. 3 from the Ordinance)
The person filing the application corrects any incompleteness and irregularities in the documents or provides additionally the required documents and information within 30 days as of the date of receipt of the operator’s notice. The time limit for providing an opinion shall commence from the date on which the additional documents and information are submitted.
| Important to know | |
![]() | The procedure for the connection of the site is terminated when the person does not rectify the incompleteness and irregularities in the documents or does not provide the additional documents and information required within а 30-day time limit. |
A request shall not be submitted in accordance with art. 8, para. 2and the following of the Ordinance, when such has been submitted in accordance with art. 140a of the SDA. On the grounds of art. 140а of the SDA, the applicant may, together with the application for design visa, request to be provided by the respective operators with the output data necessary for the design and for the connection to the technical infrastructure networks, with content in accordance with art. 140, para. 4 of the SDA. In such case, the output data and conditions for connection to the networks, provided by the respective operator, shall be enclosed to the design permit issued as per art. 140а, para. 6 of the SDA.
The respective network operator may refuse to connect a site, fully or partially, to the electric energy network, with justification of the grounds for the refusal, provided that:
- There is technical impossibility to connect the site within the stated deadline for site commissioning;
- When, due to the unavailability of the required capacity, the connection of the site leads to deterioration of the conditions for the supply of electric energy to other customers.
The refusal for connection may be appealed before the Energy and Water Regulatory Commission (EWRC) under the terms and the procedure set out in art. 22 of the Energy Act.
Issuance of a written statement by the operator and signing of a preliminary connection agreement
After the successful completion of Step 1, the network operator prepares and provides to the person that has submitted the request under item 1 above:
- Written statement regarding the conditions for the connection – in all cases; and
- Draft preliminary connection agreement – only in the cases of connection of sites of producers of electricity to the electricity networks.
The written statement regarding the conditions for connection shall be issued by the network operator within a period of 14 to 40 days, counted from the date of receipt of the request, depending on its complexity and specifics of the research.
After the issuance of the statement regarding the conditions for connection, the customer submits to the network operator a work design, part architectural and part electrical installations and installations up to the property’s boundary. The operator shall approve these parts within 7 working days, and if it is necessary to coordinate with another operator, the term shall be extended by the term of the necessary coordination, but not more than 30 days from the submission of the work designs.
In the cases where signing of a preliminary connection agreement is required, the total period for coordination of the conditions for connection and signing of a preliminary agreement is set to 25 days.
The preliminary connection agreement is concluded before the preparation of the investment project for construction or reconstruction of the connected site. Article 17, paragraph 1 of the Ordinance specifies the cases in which, following an opinion, it is necessary to conclude a preliminary connection agreement with the network operator.
| Important to know | |
![]() | The opinion is valid for a period of time (Article 16 of the Ordinance):
|
Conclusion of connection agreement
Agreement for connection of customers’ sites to the electricity network is signed between the respective network operator and:
- the person to whom a statement on the conditions for accession has been issued or with whom a preliminary contract has been concluded;
- a person who is the holder of a right of ownership or other real or personal right to use the property for which another person has been issued a statement or preliminary contract.
Until the expiry of the term of the opinion or preliminary contract and after approval of the projects and issuance of a building permit (where required under the Spatial
Development Act), the person shall submit a written request to the network operator for the conclusion of a connection contract, attaching:
- a notarized power of attorney (if represented by an attorney);
- a document certifying property rights or a lease agreement (when the opinion is issued to a person other than in the cases under Article 22 of the Energy and Water Supply Act).
When connecting facilities under Article 7, paragraph 1, items 1, 2, 3, and 14-17, the following shall also be attached to the application:
- a building permit (except under Article 22 of the Energy Efficiency Act) and/or a placement permit, where their issuance is mandatory under the Spatial Development Act;
- an approved investment project – architectural part and electrical equipment and installations of the facility in the part concerning the installation of connection equipment and access to them, in accordance with the opinion on the conditions for connection or the preliminary connection agreement.
If the documents are incomplete or do not meet the requirements, the network operator shall notify the applicant in writing within 14 days. The applicant shall have 30 days from the notification to remedy the irregularities or submit additional documents. The procedure shall be terminated if the instructions are not complied with within the specified time limit.
Pursuant to art. 22, para. 1 of the Ordinance, within 15-days from the submission of the request for concluding a connection agreement, the respective network operator shall prepare the agreement and send a written invitation to the person, who has submitted a request, for signing the connection agreement. Within 30 days from the receipt of the written invitation, and in the cases specified in art. 7, para. 1, items 2, 14, 15, 16, 17, and 18 of the Ordinance – within 15 days from the receipt of the project, the connection procedure shall be terminated. To initiate a new connection procedure for the site, the applicant shall submit a new request.
The connection agreement determines the rights and obligations of each of the parties, as well as the necessary conditions for connection of the site to the respective network, taking into account the actual technical capabilities of the electricity network in the area of the site.
The connection agreement to the electrical grid shall be terminated upon submission of a commissioning document for the connection facilities and the site, when its issuance is mandatory under the requirements of the SDA, unless otherwise determined in the agreement.
Design and construction of the technical facilities
Following the signing of the connection agreement, the respective network operator prepares and coordinates the detailed designs for the construction of the facilities for the connection of the site, for which the operator is responsible in accordance with the signed agreement.
The coordination term is 10 working days, and if coordination is needed with another operator, the deadline is extended with the term for the required coordination, but not exceeding 30 days as of the submission of the designs. The respective network operator shall coordinate the working designs with the person with whom the connection agreement has been concluded, regarding:
- The point of connection;
- The location and type of facilities on the site and the associated servitude zones;
- The boundary of ownership of the electrical facilities;
- The stages and time frame for construction.
As set out in art. 28, para 3 of the Ordinance the respective network operator starts the construction of the connection facilities after:
- The transfer of the ownership or the establishment of the right to construction in the case when in order to realise the connection facility element of the transmission or distribution network should be built in the property where the connected site is located and this is technically and constructively admissible;
- Establishment of easement rights by the owner of the property;
- Payment of the connection fee set out in the agreement.
The procedure for the design and construction of the connection facilities with regard to sites of electricity production is regulated in a similar manner, with some specifics, in articles 48 and the followingof the Ordinance.
Commissioning of customer sites and facilities for connection to electricity networks
Electricity facilities for the connection of the site to the electricity network are fed with voltage and/or are connected in parallel with the EPS, when the requirements for the commissioning of the connected site are met, which is evidenced by:
- Document for commissioning of the facilities for the connection, issued under the terms and conditions and procedure under the SDA;
- Document for commissioning of the site, issued under the terms and conditions and procedure under SDA;
- Declaration by the customer for compliance of his electric installations with the safety requirements and technical norms.
Voltage is fed only to the facilities up to the border of the ownership by the respective network operator or persons authorised by the operator within 7 days as of the date of submission of evidence by the customer that the customer has signed:
- An access agreement and transmission agreement to.through the respective network, or an access agreement under a temporary connection scheme and a transmission agreement to/through the respective network.;
- Contracts in the electricity market pursuant to art. 11, items 4 and/or art. 11 item 9, and/or art. 11, item 17 of the rules under art. 91 para. 2 of the Energy Аct.
| Fee | The fee for the various stages of the electricity network connection procedure is specific for each service provider. |
| Term | Many of the deadlines in the electricity networks connection procedure are set out in the connection agreement, as well as by the specific operator. |
| For more information | |
![]() | Indicative fees for connection and services of the various electricity distribution companies are available on the following websites: |

